FastReactPlan_-_How_to_update_event_completion_date_automatically

Article Public Number: KA-01314

Coats Digital Knowledge Article

Product: FastReactPlan

Purpose & Scope:

When user wants an event to be completed automatically when the date is falling to the target date

Solution:
Enable option “Event is used as a reminder only” in event setup dialog

Instructions:

  • Step 1: Go to Setup -> Event planning -> Framework
  • Step 2: Create new event/ update existing event -> Tick on option “Event is used as a reminder only” -> select Insert/ Update
  • Step 3: If the Event is created newly, need to go to Setup -> Event planning -> Timetables to update new event in existing Timetables
  • Step 4: Go to tab Events -> select a timetable -> click Update

    Outcome:
  • If the order is planned on plan row with target date of event “Order Trim” is 05/01/2025
  • So,when the date is falling on 01/05/2025, then event “Order Trim” will be competed automatically with date as 05/01/2025.