FastReactPlan_-_How_weekly_strip_efficiency_is_calculated
Article Public Number: KA-01312
Coats Digital Knowledge Article
Product: FastReactPlan
Below will be an example calculation: How the weekly strip efficiency is calculated in FastReactPlan.
The daily values are used to calculate a kind of weighted average for the week based on the quantities that could be produced if the efficiency was 100%. We'll start with the daily quantities which will be 3000 and for efficiencies, we'll have 52, 55 and 60 so we have:
|
Week |
Day |
Effy |
Qty |
Week |
|
|
|
|
|
Total |
|
1st Week |
13 |
52 |
392 |
392 |
|
2nd Week |
14 |
52 |
515 |
|
|
|
15 |
52 |
515 |
|
|
|
16 |
55 |
545 |
|
|
|
17 |
55 |
545 |
|
|
|
18 |
60 |
488 |
2608 |
|
|
|
|
3000 |
|
Then calculate what the quantities would be if efficiency was 100%:
|
Week |
Day |
Effy |
Qty |
Week |
|
Max Qty |
Calc |
|
|
|
|
|
Total |
|
(qty / effy) |
|
|
1st Week |
13 |
52 |
392 |
392 |
|
753.85 |
= 392 / 52 * 100 |
|
2nd Week |
14 |
52 |
515 |
|
|
990.38 |
= 515 / 52 * 100 |
|
|
15 |
52 |
515 |
|
|
990.38 |
= 515 / 52 * 100 |
|
|
16 |
55 |
545 |
|
|
990.91 |
= 545 / 55 * 100 |
|
|
17 |
55 |
545 |
|
|
990.91 |
= 545 / 55 * 100 |
|
|
18 |
60 |
488 |
2608 |
|
813.33 |
= 488 / 60 * 100 |
|
|
|
|
3000 |
|
|
|
|
Then the weekly total of those:
|
Week |
Day |
Week |
|
Max Qty |
Week |
|
|
|
Total |
|
(qty / effy) |
Total |
|
1st Week |
13 |
392 |
|
753.85 |
753.85 |
|
2nd Week |
14 |
|
|
990.38 |
|
|
|
15 |
|
|
990.38 |
|
|
|
16 |
|
|
990.91 |
|
|
|
17 |
|
|
990.91 |
|
|
|
18 |
2608 |
|
813.33 |
4775.92 |
and finally an averaged efficiency for the week:
|
Week |
Day |
Week |
|
Max Qty |
Week |
|
Week |
Calc |
|
|
|
Total |
|
(qty / effy) |
Total |
|
Effy |
|
|
1st Week |
13 |
392 |
|
753.85 |
753.85 |
|
52.0 |
= 392 / 753.85 * 100 |
|
2nd Week |
14 |
|
|
990.38 |
|
|
|
|
|
|
15 |
|
|
990.38 |
|
|
|
|
|
|
16 |
|
|
990.91 |
|
|
|
|
|
|
17 |
|
|
990.91 |
|
|
|
|
|
|
18 |
2608 |
|
813.33 |
4775.92 |
|
54.6 |
= 2608 / 4775.92 * 100 |